Process capability (Cp / Cpk) calculator
A free process capability calculator. Paste your measurements and the specification limits to get the mean, sigma, Cp, Cpk, Cpu and Cpl, with a plain-language verdict and every step worked through.
Enter at least two measurements.
- MR̄ = average of |xᵢ − xᵢ₋₁|
- σ = MR̄ ÷ d₂ (1.128)
- Cp = (USL − LSL) ÷ 6σ
- Cpu = (USL − mean) ÷ 3σ
- Cpl = (mean − LSL) ÷ 3σ
- Cpk = min(Cpu, Cpl)
What Cp and Cpk tell you
A specification has limits: a slab must be 300 mm thick, give or take 10. Process capability asks whether the way you actually do the work can stay inside those limits.
- Cp compares the width of the specification with the spread of the process (6σ). It says whether the process could fit if it were perfectly centred.
- Cpk takes the centre into account: the distance from the mean to the nearer limit, divided by 3σ. It says whether the process does fit where it actually runs.
As a rule of thumb, a Cpk of 1.33 or more is capable, 1 to 1.33 is just capable with little margin, and below 1 means some output will fall outside the specification.
How σ is estimated here
This calculator uses the moving range method of the individuals (I-MR) chart: the average gap between one measurement and the next, divided by 1.128. It measures short-term variation, which is why the measurements should be entered in the order they were taken. VanillaPM's quality workspace uses the same method on a project's own measurements.
Common mistakes
- Judging capability on a process that is not stable. Check the control chart first; capability on an out-of-control process means little.
- Too few measurements. Twenty or more gives a more trustworthy figure than five.
- Reporting Cp alone. A process can have a good Cp and still be off-centre and producing defects.