Communication channels calculator
A free communication channels calculator — enter the number of people to get the number of communication channels, n(n − 1) / 2, and see how many are added when people join.
- Channels = n(n − 1) ÷ 2
- After = (n + k)(n + k − 1) ÷ 2
The formula
Every pair of people who might talk to each other is one channel. With n people there are n(n − 1) ÷ 2 channels: 5 people have 10, 10 have 45, 20 have 190.
Why it matters
Communication effort grows far faster than the head count. Adding two people to a team of eight adds 17 channels, not two. That's why larger projects need a planned structure (a communications plan) rather than everyone talking to everyone, and why a late addition to the team can slow things down before it speeds them up.
On the PMP exam
Questions often give a team size, add a few people, and ask how many channels were added. Work out both totals and subtract; the calculator shows each step.