PERT / three-point estimate calculator
A free PERT and three-point estimating calculator — enter optimistic, most likely and pessimistic estimates to get the beta-PERT and triangular expected values, the standard deviation and 68%, 95% and 99.7% ranges.
Expect O ≤ M ≤ P.
- Expected = (O + 4M + P) ÷ 6
- σ = (P − O) ÷ 6
- Variance = σ²
- 68% range (±1σ)
- 95% range (±2σ)
- 99.7% range (±3σ)
Why three points
A single-number estimate hides how uncertain it is. Three-point estimating asks for three:
- O, optimistic: if things go well (not the miracle case).
- M, most likely: what usually happens.
- P, pessimistic: if things go badly (not the disaster case).
Beta-PERT, (O + 4M + P) ÷ 6, weights the most likely value four times. Triangular, (O + M + P) ÷ 3, weights all three equally, so it comes out higher when the pessimistic case is far away.
Turning the spread into a commitment
The standard deviation, (P − O) ÷ 6, measures the uncertainty. Roughly 68% of outcomes fall within ±1σ of the expected value, 95% within ±2σ and 99.7% within ±3σ. If you need to commit to a date or a budget, the ±2σ upper bound is one you can usually stand behind.
To combine activities along a path, add their variances (σ²), not their standard deviations, then take the square root.
On a real project
The schedule lesson uses three-point estimates on the Coral Ridge sample, and shows why the critical path decides which of them matter.