Procurement management plan template

A free procurement management plan template in Word and Markdown — make-or-buy decisions, procurement packages with lead times and order-by dates, contract types, selection criteria, approval limits and risks.

Download Word (.docx) Download Markdown (.md) Free · no sign-up · opens in Word, Excel, Google Docs/Sheets and LibreOffice

What's inside

  1. Purpose and scopeWhat will be bought, what will be done in-house, and who keeps this plan.
  2. Make-or-buy decisionsFor each major item, why it is bought rather than done in-house (or the reverse).
  3. Procurement packagesOne line per package: what, how bought, contract type, lead time and dates (table below).
  4. Contract typesFixed price, cost-reimbursable or time and materials, and why each fits its package.
  5. Selection criteriaHow bids are evaluated: price, technical score, experience, local content, and the weightings.
  6. Roles and approval limitsWho can issue tenders, evaluate, and sign contracts, and up to what value.
  7. Risks and constraintsLong-lead items, import rules, currency, single suppliers.
  8. Performance and closureHow supplier performance is checked and how contracts are closed.

Includes a ready-made table with 8 columns: Package · Method (tender / quotes / direct) · Contract type · Estimated value · Lead time (days) · Needed on site · Order by · Owner.

What a procurement plan is

The procurement plan says what the project will buy, how it will buy it, and when. Its heart is the list of procurement packages: each with a method, a contract type, a value, a lead time and the date it must be ordered by to arrive when the work needs it.

When to use it

Early in planning, because long-lead items can drive the schedule. Update it as packages are tendered, awarded and closed.

How to fill it in

  1. Decide make or buy for each major item, and say why.
  2. List the packages in the table. For each, work back from the date it is needed on site: order by = needed on site − lead time. The order-by date calculator does this for a whole list.
  3. Choose the contract type that fits the risk: fixed price when the scope is clear, cost-reimbursable when it isn't, time and materials for small or urgent work.
  4. Set the selection criteria and their weightings before the bids arrive.
  5. Write down who can approve what, and up to which value.

Common mistakes

  • Lead times that leave out your own approvals and shipping.
  • Choosing a fixed price for work nobody can define yet. The supplier will price the risk, or claim for it later.
  • Packages the schedule doesn't know about, so their order dates are missed.

See it used on a real project: Pr5 · Plan and manage procurement