Procurement management plan template
A free procurement management plan template in Word and Markdown — make-or-buy decisions, procurement packages with lead times and order-by dates, contract types, selection criteria, approval limits and risks.
What's inside
- Purpose and scopeWhat will be bought, what will be done in-house, and who keeps this plan.
- Make-or-buy decisionsFor each major item, why it is bought rather than done in-house (or the reverse).
- Procurement packagesOne line per package: what, how bought, contract type, lead time and dates (table below).
- Contract typesFixed price, cost-reimbursable or time and materials, and why each fits its package.
- Selection criteriaHow bids are evaluated: price, technical score, experience, local content, and the weightings.
- Roles and approval limitsWho can issue tenders, evaluate, and sign contracts, and up to what value.
- Risks and constraintsLong-lead items, import rules, currency, single suppliers.
- Performance and closureHow supplier performance is checked and how contracts are closed.
Includes a ready-made table with 8 columns: Package · Method (tender / quotes / direct) · Contract type · Estimated value · Lead time (days) · Needed on site · Order by · Owner.
What a procurement plan is
The procurement plan says what the project will buy, how it will buy it, and when. Its heart is the list of procurement packages: each with a method, a contract type, a value, a lead time and the date it must be ordered by to arrive when the work needs it.
When to use it
Early in planning, because long-lead items can drive the schedule. Update it as packages are tendered, awarded and closed.
How to fill it in
- Decide make or buy for each major item, and say why.
- List the packages in the table. For each, work back from the date it is needed on site: order by = needed on site − lead time. The order-by date calculator does this for a whole list.
- Choose the contract type that fits the risk: fixed price when the scope is clear, cost-reimbursable when it isn't, time and materials for small or urgent work.
- Set the selection criteria and their weightings before the bids arrive.
- Write down who can approve what, and up to which value.
Common mistakes
- Lead times that leave out your own approvals and shipping.
- Choosing a fixed price for work nobody can define yet. The supplier will price the risk, or claim for it later.
- Packages the schedule doesn't know about, so their order dates are missed.
See it used on a real project: Pr5 · Plan and manage procurement