Decision log template
A free project decision log template in Excel and CSV — the decision, options considered, reason, who decided and at what level, impact, related issue, risk or change, who was told, review date and status.
What's inside
| Column | What goes in it |
|---|---|
| ID | DEC-001, DEC-002 … |
| Date | |
| Decision | What was decided, in one sentence |
| Options considered | |
| Reason | Why this option |
| Decided by | The person or body with the authority |
| Level | drop-down Project manager, Sponsor, Steering committee, Change board, Board |
| Impact | drop-down Scope, Schedule, Cost, Quality, Risk, Several |
| Related item | Issue, risk or change request ID |
| Communicated to | |
| Review date | When to check the decision still holds |
| Status | drop-down Proposed, Approved, Rejected, Superseded |
The Excel file has three sheets: the blank register, a filled example from the Coral Ridge Resort sample project, and how to use each column. The CSV is the blank header row only.
What a decision log is
A record of the significant decisions on a project: what was decided, what else was considered, why, and who had the authority. Months later, when someone asks "why did we do it this way?", the answer is there, and nobody has to rely on memory.
When to use it
For any decision that affects scope, schedule, cost, quality or risk, or that someone might later question. Small day-to-day choices don't need it.
How to fill it in
- State the decision in one sentence.
- List the options considered, including doing nothing.
- Give the reason. If you used a decision tree or a business case, say so.
- Record who decided and at what level, and check it was within their authority.
- Link the related item: the issue, risk or change request that led to it.
- Record who was told, and set a review date for decisions that may need revisiting.
Common mistakes
- Decisions made in meetings and never written down.
- No reason recorded, so the decision gets reopened every time someone new joins.
- Decided at the wrong level: check the approval limits in your governance plan.
See it used on a real project: B1 · Establish project governance