# Change request form

_Free template from VanillaPM · vanillapm.com/learn/templates_

> Replace each line in italics with your own text. Delete the guidance when you are done.

## Request details

_Change request number, title, date raised, and who is asking._


## Description of the change

_What would change, exactly: the deliverable, requirement, date or budget line affected._


## Reason and benefit

_Why it is needed, and what happens if it is not made._


## Type

_Corrective action, preventive action, defect repair, or an update to the plan or a requirement._


## Impact assessment

_The effect on scope, schedule, cost, quality, risk and resources (table below). Say "none" rather than leaving a blank._


| Area | Impact | Amount (days or money) | Notes |
|---|---|---|---|
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |

## Options considered

_The alternatives, including doing nothing, and why this one is recommended._


## Decision

_Approved, rejected or deferred; who decided (sponsor, change control board) and when, with any conditions._


## Implementation

_Who updates which baselines and documents, and how the people affected are told._


---

## Example (Coral Ridge Resort sample)

**Request details:** CR-014, "Add a rooftop bar", raised 12 May 2027 by the operator (Corvane).

**Impact assessment:** Cost +USD 420k; schedule +3 weeks on the roof works (not critical); structural check of the roof slab needed.

**Decision:** Approved by the steering committee, 2 Jun 2027, funded from the owner, not contingency.