# Business case

_Free template from VanillaPM · vanillapm.com/learn/templates_

> Replace each line in italics with your own text. Delete the guidance when you are done.

## Executive summary

_Three or four lines a busy approver can read first: the need, the recommended option, its cost and the decision you want. Write it last._


## Business need and problem statement

_The problem or opportunity, with the facts that show it is real. Describe the need without naming the solution ("staff in Denver by 1 September", not "a Denver office")._


## Strategic alignment

_How this supports the organisation's goals or strategy, and what happens to those goals if nothing is done._


## Options considered

_Every realistic way to meet the need, always including "do nothing" as the baseline (table below). For each: rough cost, benefits, what it cannot do, and its main risks._


| Option | Cost (estimate) | Benefits | What it cannot do | Main risks |
|---|---|---|---|---|
| | | | | |
| | | | | |
| | | | | |
| | | | | |

## Recommended option

_The option you recommend and why it meets the need better than the others. Name a fallback if the first choice fails._


## Costs and benefits

_What the recommended option costs to deliver and to run, and the benefits, split into the ones you can count (money, time) and the ones you cannot count yet. Compare cost with benefit, not with revenue._


## Risks and assumptions

_The few big uncertainties and the things you are taking as true without proof. Each assumption also goes in the assumption log._


## Recommendation and decision sought

_One sentence the approver can say yes or no to: what to approve, how much to release now, and by when._


## Approval

_Name, role, signature and date of the sponsor who owns the business case (and anyone else who must approve)._


---

## Example (Coral Ridge Resort sample)

**Business need and problem statement:** The owner's beachfront land in Cox's Bazar earns nothing, while five-star rooms on the coast are in short supply.

**Options considered:** A. Build a 220-key five-star resort. B. Build a smaller three-star hotel. C. Sell the land. D. Do nothing: hold the land.

**Costs and benefits:** Option A: USD 48M to build, about USD 7M a year to run. Counted: room revenue; NPV USD 9.4M at a 12% discount rate, IRR 18.2%. Not yet counted: the developer's name on the coast, local jobs.

**Recommendation and decision sought:** Approve Option A in principle and fund the detailed design; full funding is decided at the design review.